Marine and Heavy Construction |
|
Lakes and Rivers Contracting, Inc. |

|
Bayview Lane Bridge—McHenry, IL. |
|
The existing structure, built is 1922, was a 14 span cast in place bridge on a wood pile foundation |
|
New bridge deck was set with both land based and barge based equipment. The new five span deck was set and anchored in two days. |
Completion Date: 11/15/04 |
Job Number: 03004 |
Progress Pictures |
|
The new structure was built adjacent to the existing structure so traffic could be maintained on the old structure until completion. Due to a thick seam of peat, the new bridge approaches were constructed of a reinforced geogrid mat |
|
Existing Structure to be Replaced |
|
Bridge Approach Realigned and Stabilized |
|
New Precast—Prestressed Bridge Deck |
|
Project is located just east of Johnsburg, IL. where Bayview Lane crosses the channel between Pistakee Lake and Meyers Lake |
|
Owner: IDOT |
|
Engineer: Smith Engineering |




|
Removal of Exisiting Bridge ng Bridge |
|
The existing structure was sawcut and removed in slabs. The existing pile caps were cut into manageable pieces with a wire saw and removed. |